To cover low strength mixes and train staff on acceptance of Block Fill concrete

Key Points :
To establish a process for the acceptance of low-strength and 'block fill' concrete poured into precast concrete moulds, with a primary focus on the removal of lifting anchors before pouring the block. This procedure aims to ensure the safety and quality of precast concrete blocks after manufacturing.

Health and Safety:

  • All staff must wear PPE (safety glasses, gloves, vests, and steel-toed boots.)
  • Equipment Safety: Regularly inspect lifting gear; only trained operators.
  • Lifting Techniques: Use proper techniques to prevent injuries.
1. Safety Briefing:

  • Conduct a pre-task safety briefing.
  • Ensure all personnel wear appropriate PPE.

2. Mix Check on Truck Arrival:

  • Confirm concrete mix with the truck driver.
  • Verify mix suitability.

3. Lifting Anchor Removal:

  • Remove lifting anchors before pouring.
  • Demoulded blocks should not have lifting anchors to prevent potential damage.

4. Additional Considerations:

  • Emphasize adherence to safety guidelines.
  • Train on proper lifting techniques and encourage teamwork.

5. Emergency Procedures:

  • Provide emergency procedure training.
  • Ensure personnel know evacuation routes and emergency equipment locations.
6. Review and Assessment:

  • Periodically review and assess effectiveness.